Campaign Milestone
Records: 8
| ID | Campaign | Milestone Type | Planned At | Forecast At | Actual At | |
|---|---|---|---|---|---|---|
|
|
1 | Demonstration major maintenance shutdown | SCOPE_FREEZE | 2027-01-15 00:00 | 2027-01-22 00:00 | - |
|
|
2 | Demonstration major maintenance shutdown | MATERIAL_FREEZE | 2027-02-01 00:00 | 2027-02-01 00:00 | - |
|
|
3 | Demonstration major maintenance shutdown | SHUTDOWN_START | 2027-03-01 00:00 | 2027-03-01 00:00 | - |
|
|
4 | Demonstration major maintenance shutdown | RETURN_TO_SERVICE | 2027-03-21 00:00 | 2027-03-21 00:00 | - |
|
|
5 | Mill reline and conveyor shutdown | SCOPE_FREEZE | 2026-11-23 00:00 | 2026-11-23 00:00 | - |
|
|
6 | Mill reline and conveyor shutdown | SHUTDOWN_START | 2026-12-07 00:00 | 2026-12-07 00:00 | - |
|
|
7 | Mill reline and conveyor shutdown | MECHANICAL_COMPLETE | 2026-12-12 00:00 | 2026-12-12 00:00 | - |
|
|
8 | Mill reline and conveyor shutdown | CLOSEOUT | 2026-12-14 00:00 | 2026-12-14 00:00 | - |